Document Type
Thesis
Date of Award
5-31-1988
Degree Name
Master of Science in Civil Engineering - (M.S.)
Department
Civil and Environmental Engineering
First Advisor
Edward G. Dauenheimer
Second Advisor
Walter Konon
Third Advisor
John R. Schuring
Abstract
The problem addressed in this thesis is that of determining the practicability of equating measures of network and resource characteristics to the early finish date of a project which is constrained by resources. The output of standard critical path calculations along with information on resource profiles that are easy to calculate can be of use in estimating resource constrained project duration.
Twenty two different equations ( developed by Hall) were used to find the estimated project finish dates. These results were compared to the schedule resulting from the application of the heuristic rule of minimum activity float. It is shown that the calculations may be used as a substitute to resource leveling procedure.
Recommended Citation
Karmakar, Rabindra Nath, "Determination of project duration for resource constrained projects without using resource scheduling procedure" (1988). Theses. 3112.
https://digitalcommons.njit.edu/theses/3112